O&M Submittal

Submittal Process


  • Field inspection needs to be set up with the Town Utilities Inspector, Kevin Rodgers, 803-358-1542.
  • Two sets of as-built drawings, with appropriate easements.
  • Finals to be signed and sealed. Once approved, an electronic copy is to be sent by email. View As-Built Plan Data (PDF).
  • Deeds and Easements: Easements are to be shown and noted on referenced article be it "as-builts," recorded bonded plat, or recorded final plat.
  • Construction cost should include the Project or Phase Project that the deed and easements are recorded. They should be submitted by email.

Water


  • A copy of the bacteriological tests.

Sewer


  • Gravity (PDF)
    • Low pressure air test
    • Vacuum test
    • Video inspection of line with camera equipped with Inclinometer, submitted on DVD format (not CD), and written report.
  • Forcemain
    • Hydrostatic test: 150* pounds per square inch for 2 hours (*depends on head conditions)

Lift Station